
How to show the critical path in Merlin Project and see why an activity is critical, or no longer critical.

Merlin Project automatically recognizes whether or not activities are on critical path. On forwards planned projects, they are the activities which may change the end of the project.
The glossary entry Critical Path explains what the critical path is and how to calculate it by hand with a forward and backward pass. This guide shows how Merlin Project calculates and displays it.
The Critical Path in Merlin Project
If you have for example just two activities (A and B) starting today with a duration of 2 for A and 5 days for B. ,Activity B' with the longer duration (5 days) defines the end of the project and it is thus on critical path.

If the critical path is not visible, choose View › Show Critical Path or click the lightning bolt in the toolbar.
If you change the duration of the ,Activity A' from 2 days to to 5.5 days, then ,Activity A' will be on the critical path, while the other activity won't.

If you complete an activity which was until now on the critical path, it won't belong anymore onto the critical path, as this activity is now fixed and cannot push the expected end anymore.

Using the Column "Expected Critical"
Tip: I can add the column “Expected Critical” and can see where the system has assigned items as being on the critical path.
"Is there a way that this can be assigned?"
No. Let us explain how the Critical columns work.
There are two columns related to the critical path in Merlin Project:
- Planned Critical
- Expected Critical
They are both calculated:
- Planned Critical shows if the activity is on the critical path due to its planned values.
- Expected Critical shows if the activity is on the critical path due to its actual values. It is always false, for an activity which is 100% complete.
If you have any questions about this blog article or would like to discuss it, we look forward to your contribution in our forum.