In some predefined 'Work breakdown' and 'Report' views and in the 'Plan' inspector, Merlin shows Status information. The status is presented in form of traffic light-colored shapes which are abstract but easily identifiable even to those with vision problems:

The activity status

Black = check mark
Red = square
Yellow = triangle
Green = circle
No colour = empty circle


The activity status can not be assigned manually, as it is a calculated value. These are its possible states:

The activity status

Black: Activity is complete
Red: Activity behind schedule (>10%)
Yellow: Activity slightly behind schedule (=<10%)
Green: Activity on time
No colour: Future or unscheduled activity, activity pending