Merlin Project: Using Lead / Lag

Merlin Project Support

You are using Merlin Project and appreciate its dynamic planning options for scheduling? Then you already know how to use depedencies.

Linking activities in different ways is very easy and has been explained in one of our previous posts. If not already done so, just take a look at that post.

How to define a lead or lag between activities?

This is how to proceed:

Dependency Inspector

Lead

  • Two activities ,A1' and ,A2' are linked by a dependency
  • Select the dependency
  • Within the ,Dependency' inspector set ,5 days' for ,Lead/Lag'
  • this will push ,A2' 5 days in the future


This is what it should look like:

Lead between activities


Lag

  • Now add a third activity ,A3'
  • Link ,A2' and ,A3' by an ,End to Start' dependency
  • Select this dependency
  • Within ,Dependency' inspector set ,-3 days' for ,Lead/Lag'
  • this will push ,A3' to start 3 days before the expected end of ,A2'

Again, this is an example what it should look like:

Lag between activities

Using dependencies your scheduling stays flexible, even more if using lead/lag values.

Publié par Peter Meier le 03.05.2018 dans Produits
Mots-clés: merlin-project assistance macOS

Merlin Project sur Mac et iPad

Vos idées, notre magie – Réalisez vos projets en toute simplicité!
Essayez maintenant gratuitement pendant 30 jours.