Back to glossary

Glossary

Cost Performance Index (CPI)

CPI, Cost Efficiency Index

The cost performance index (CPI) shows how much planned project value you get for every dollar or euro spent. The formula is CPI = EV / AC: earned value divided by actual cost. A CPI below 1 means a cost overrun; a CPI above 1 means the completed work cost less than planned.

The CPI is a key figure of earned value analysis. It answers a question that a simple comparison of planned and actual cost leaves open: did the team deliver the planned work for the money spent?

How do you calculate the cost performance index?

CPI = EV / AC

Both values refer to the same cutoff date, the status date.

Example: calculating the CPI

Example: a team builds a customer portal with a budget (BAC) of 20,000 EUR. On the status date the portal is 40% complete and actual costs are 10,000 EUR.

Value Calculation Result
Budget (BAC) 20,000 EUR
Earned value (EV) 40% × 20,000 EUR 8,000 EUR
Actual cost (AC) 10,000 EUR
CPI 8,000 / 10,000 0.8
Cost variance (CV) EV − AC = 8,000 − 10,000 −2,000 EUR

A CPI of 0.8 means: for every euro spent, the team completed work with a planned value of 80 cents. If efficiency stays the same, the project will cost BAC / CPI = 20,000 / 0.8 = 25,000 EUR, 5,000 EUR more than planned. This forecast is called the estimate at completion (EAC).

How do you interpret the CPI?

CPI Meaning Example
greater than 1 Under budget: the work costs less than planned CPI 1.25: 1.25 EUR of planned value per euro spent
equal to 1 Exactly on budget CPI 1.0: earned value and actual cost match
less than 1 Over budget: the work costs more than planned CPI 0.8: the completed work costs 25% more than planned

The CPI says nothing about the schedule. A project with a CPI of 1.1 can still be weeks behind. The schedule performance index (SPI = EV / PV) covers the timeline. Read both values together:

Common mistakes with the CPI

Where does Merlin Project show the CPI?

Merlin Project calculates the Cost Performance Index (CPI) automatically once costs and actual values are maintained, as BCWP / ACWP. BCWP (budgeted cost of work performed) is the earned value, ACWP (actual cost of work performed) the actual cost.

The ready-made view View › Work Breakdown › Earned Value shows all earned value key figures as a table and time phase chart. Add the CPI and other earned value fields to any activity, assignment, or resource view with Insert › Column. All earned value fields refer to the status date; check it in the Project Settings before you evaluate the CPI.

To set up budget and costs so the numbers add up, read Effectively Manage Budget and Costs.

Run projects that actually ship.

One app for your project plan, native on every Apple device.