Back to glossary

Glossary

Triple Constraint

Project Management Triangle, Iron Triangle, Project Triangle

The triple constraint (also project management triangle or iron triangle) describes the three factors that limit every project: scope, time, and cost. Quality sits in the middle and depends on all three corners. If you change one corner, you have to adjust at least one other, or quality pays the price.

Triple Constraint

The model goes back to Martin Barnes. In 1969 he drew a triangle with cost, time, and quality at its corners for his course "Time and Cost in Contract Control".1 Most current versions put scope, time, and cost at the corners and quality in the middle.

What do the three corners mean?

Decide before the start which corner is fixed. For a trade fair booth it is usually the date; for a fixed-price contract, the budget. This ranking settles every trade-off later.

Triple constraint: an example

Example: an agency builds an online shop. The plan: 12 features in 10 weeks with 2 developers at 2,500 EUR per week each, so 50,000 EUR. The client wants to launch 2 weeks earlier because a campaign starts. The agency calculates three options:

Option Scope Time Cost Consequence
A: third developer 12 features 8 weeks 60,000 EUR (3 × 8 × 2,500) Budget rises by 20%, plus onboarding
B: cut scope 9 features 8 weeks 40,000 EUR (2 × 8 × 2,500) 3 features follow after launch
C: only move the deadline 12 features 8 weeks 40,000 EUR Testing and polish drop out, quality falls

Option C breaks the triangle: the deadline moves up, scope and team stay the same, so quality absorbs the difference. The fixed corner decides between A and B. If the budget is capped, only B remains. Option A is known as crashing; expecting the third developer to be fully productive right away is optimistic, though, see Brooks's law. A fourth route is fast tracking: the team overlaps work steps, saves time without extra staff, and accepts a higher risk of rework.

What extensions of the triple constraint exist?

Common mistakes

How do you manage the triple constraint in Merlin Project?

Merlin Project covers all three corners: scope as activities and groups in the Work Breakdown, time through work and duration, dependencies, and the work calendar, cost through resource rates and fixed costs. Change one value and Merlin Project calculates the effect on dates and costs.

The plan/actual comparison shows whether the project is drifting out of the triangle. Enter an earlier date in the Reference Date field of the Project Settings, for example the day the project was approved. Merlin Project then shows the dates planned at that time as gray reference bars in the Gantt chart. You don't need to save a baseline beforehand, because every Merlin document contains the project history. The views Plan/Actual Comparison (Time) and Plan/Actual Comparison (Cost) show planned and expected values side by side, the cost view including budget and balance.

You can rate risks along the triangle too: in the inspector of a risk, score Scope Impact, Cost Impact, and Deadline Impact from 0 to 5 points each.

Run projects that actually ship.

One app for your project plan, native on every Apple device.