Merlin to Project 2013 – Exchanging Files


You want to exchange Merlin Project files with MS Project users? Here we show you how you can export your project accordingly.
To exchange Merlin Project files with MS Project users, choose 'File > Export… > MS Project'.

In our learning path we show you how to master Merlin Project and manage your projects efficiently.
This creates a MS Project XML file.
Project 2013 users open the thus exported XML MS Project files as follows:
-
Click the 'File' tab.
-
Click 'New' on the left side of the Project window.
-
Choose 'New from existing project'

- Switch from 'Projects' to 'XML Format'

- Navigate to the xml project, select and click on 'Open'

And finally select 'As a new project' in the import wizard of Project 2013.

This article was last updated on February 27, 2025.
If you have any questions about this blog article or would like to discuss it, we look forward to your contribution in our forum.