Back to glossary

Glossary

Lessons Learned

project retrospective, post-project review, lessons learned workshop

Lessons learned are the experiences from a project that a team records so that later projects benefit from them. The team collects them in a review, usually a workshop at the end of a phase or project. A single insight is a "lesson learned"; the documented collection is often called the lessons learned register or report.

Lessons learned belong to the closing process, but not only there. If you only ask what went wrong at the end of a long project, you get memories instead of facts. Plan a short round after every phase or major milestone as well.

How Does a Lessons Learned Workshop Work?

  1. Prepare: The project manager gathers facts: planned and actual dates and costs, risks that occurred, status reports. Every participant notes their three most important observations in advance.
  2. Set the frame: A neutral facilitator explains the goal. The team looks for causes and improvements, not for someone to blame.
  3. Collect: Each person names what went well and what did not. The facilitator clusters the input by topic, such as planning, communication or technology.
  4. Analyze causes: For the most important topics, the team keeps asking why until a cause appears that it can change next time.
  5. Record actions: Every insight gets a recommendation, a person responsible and a storage location where the next project team will find it.

Set a fixed time frame, for example 90 minutes, and if in doubt shorten the collecting phase, not the actions.

Questions for the Project Review

Copy these questions into your workshop invitation:

Example: A Lessons Learned Entry

Field Content
Topic Delivery of Wi-Fi hardware for the office move
Observation The hardware arrived nine days later than promised.
Cause Ordered only after the floor plan was approved, no buffer before the moving date.
Impact Two days of work without a network, rented equipment for 1,200 euros (example values).
Recommendation Ask about long lead times at project start and order critical hardware before detailed planning.
Owner Head of IT, for all future site projects

A good entry describes a concrete situation and ends with an action. "Improve communication" is not a lesson learned; "Weekly status report to the sponsor from project start" is.

Common Mistakes

How Do You Record Lessons Learned in Merlin Project?

Merlin Project stores insights directly in the project document:

Run projects that actually ship.

One app for your project plan, native on every Apple device.