Merlin Project: Adjusting the default calendar

You use Merlin Project to plan your projects? Then you already know how to set the Project Calendar in Merlin Project.
In case you don't - You'll find the Project Calendar in the Project Settings.
New documents come with following pre-defined calendars: Standard, Night Shift, 24 hours. By default the Standard calendar is selected as project calendar. So the tasks of your project will be scheduled within 8 hours distributed 8am - 12pm and 1pm - 5pm Mondays to Fridays.
How should you proceed if the members of your team are available for this project not 8 but 7 hours per day?
En savoir plus...Merlin Project: Calendar as visual reference not affecting planning

You use Merlin Project to plan your projects? Then you already know how to set the Project Calendar in Merlin Project.
In case you don't - You'll find the Project Calendar in the Project Settings.
New documents come with following pre-defined calendars: Standard, Night Shift, 24 hours. By default the Standard calendar is selected as project calendar. So the tasks of your project will be scheduled within 8 hours distributed 8am - 12pm and 1pm - 5pm Mondays to Fridays.
How should you proceed if you have a calendar that should only serve as a visual reference for planning certain work?
En savoir plus...Merlin Project: Resources in full and part-time employment

You use Merlin Project to plan your projects? Then you already know how to set the Project Calendar in Merlin Project.
In case you don't - You'll find the Project Calendar in the Project Settings.
New documents come with following pre-defined calendars: Standard, Night Shift, 24 hours. By default the Standard calendar is selected as project calendar. So the tasks of your project will be scheduled within 8 hours distributed 8am - 12pm and 1pm - 5pm Mondays to Fridays.
How should you proceed when some of your resources are at full-time employment and some others work only 4 hours a day?
En savoir plus...Faites connaissance avec nos formateurs du Merlin Project
Aujourd'hui : Philippe Lauper de Neuchâtel en Suisse

En tant que fondateur de Prefix, Philippe Lauper offre à ses clients de l’accompagnement et de la formation en gestion de projet. Il organise et modère également des ateliers de développement d’équipe.
Philippe Lauper a 20 ans d’expérience en gestion de projet dans les milieux industriels, administratifs et académiques, mais également dans des manifestations sportives et culturelles. Plus particulièrement, il a eu l’opportunité d’être le chef de projet de l’aventure Solar Impulse, l’avion qui a réussi un tour du monde propulsé à l’énergie solaire.
En savoir plus...Merlin Project 7.2.2 Is Released

We have just released the version 7.2.2. This free update is important for Merlin Project.
- Update your Mac versions in Merlin Project for free with "Check for updates…".
- The version for the iPad and iPhone will be released after review in the App Store automatically.
We have also updated Merlin Project Express. The new versions will be provided in the Mac App Store or at SetApp – right after its review.