Merlin Project: Adjusting the default calendar

News from the Support team

You use Merlin Project to plan your projects? Then you already know how to set the Project Calendar in Merlin Project.

In case you don't - You'll find the Project Calendar in the Project Settings.
New documents come with following pre-defined calendars: Standard, Night Shift, 24 hours. By default the Standard calendar is selected as project calendar. So the tasks of your project will be scheduled within 8 hours distributed 8am - 12pm and 1pm - 5pm Mondays to Fridays.

How should you proceed if the members of your team are available for this project not 8 but 7 hours per day?

En savoir plus...

Publié par Peter Meier le 22.03.2021 dans Produits
Mots-clés: merlin-project-express merlin-project assistance macOS

Merlin Project: Calendar as visual reference not affecting planning

News from the Support team

You use Merlin Project to plan your projects? Then you already know how to set the Project Calendar in Merlin Project.

In case you don't - You'll find the Project Calendar in the Project Settings.
New documents come with following pre-defined calendars: Standard, Night Shift, 24 hours. By default the Standard calendar is selected as project calendar. So the tasks of your project will be scheduled within 8 hours distributed 8am - 12pm and 1pm - 5pm Mondays to Fridays.

How should you proceed if you have a calendar that should only serve as a visual reference for planning certain work?

En savoir plus...

Publié par Peter Meier le 15.03.2021 dans Produits
Mots-clés: merlin-project-express merlin-project assistance macOS

Merlin Project: Resources in full and part-time employment

News from the Support team

You use Merlin Project to plan your projects? Then you already know how to set the Project Calendar in Merlin Project.

In case you don't - You'll find the Project Calendar in the Project Settings.
New documents come with following pre-defined calendars: Standard, Night Shift, 24 hours. By default the Standard calendar is selected as project calendar. So the tasks of your project will be scheduled within 8 hours distributed 8am - 12pm and 1pm - 5pm Mondays to Fridays.

How should you proceed when some of your resources are at full-time employment and some others work only 4 hours a day?

En savoir plus...

Merlin Project 7.2.2 Is Released

News about Merlin Project

We have just released the version 7.2.2. This free update is important for Merlin Project.

  • Update your Mac versions in Merlin Project for free with "Check for updates…".
  • The version for the iPad and iPhone will be released after review in the App Store automatically.

We have also updated Merlin Project Express. The new versions will be provided in the Mac App Store or at SetApp – right after its review.

Publié par Frank Blome le 02.03.2021 dans Produits
Mots-clés: merlin-project merlin-project-express version

Merlin Project: Resources in Day and Night Shift

News from the Support team

You use Merlin Project to plan your projects? Then you already know how to set the Project Calendar in Merlin Project.

In case you don't - You'll find the Project Calendar in the Project Settings.
New documents come with following pre-defined calendars: Standard, Night Shift, 24 hours. By default the Standard calendar is selected as project calendar. So the tasks of your project will be scheduled within 8 hours distributed 8am - 12pm and 1pm - 5pm Mondays to Fridays.

If your project should be accomplished completely by night work, simply select the Night Shift calendar in the Project Settings.

But how should you proceed when some of your resources are able to work 8 hours during the day and some others 8 hours at night?

En savoir plus...

Publié par Peter Meier le 01.03.2021 dans Produits
Mots-clés: merlin-project-express merlin-project assistance macOS

Merlin Project sur Mac, iPad et Apple Vision Pro

Vos idées, notre magie – Réalisez vos projets en toute simplicité!
Essayez maintenant gratuitement pendant 30 jours.