Understanding and Resolving Scheduling Conflict: Dependency order is violated

Merlin Project Support

From time to time we receive in support following question:
Why does Merlin show some text or dependency lines in red?

Understanding and Resolving Scheduling Conflict - Dependency order is violated

These are rows with scheduling conflicts.

Just hover with the mouse over a red colored text. Merlin will show the current scheduling conflicts in a tool tip.

Understanding and Resolving Scheduling Conflict - Dependency order is violated
Understanding and Resolving Scheduling Conflict - Dependency order is violated

To see all scheduling conflicts, just call 'Window > Show warnings' and switch to the 'Scheduling' tab.

Understanding and Resolving Scheduling Conflict - Dependency order is violated

The conflict Dependency order is violated in the selected row occurs because - due to date constrains on the start and end values - the successor is currently expected to start before the predecessor ends.

Resolving this conflict

Option 1 - Actual values but no actual progress

Is the actual progress on successor (row #4) entered by mistake? So the activity #4 hadn't been started at all and there is no actual progress on it?

Understanding and Resolving Scheduling Conflict - Dependency order is violated

Remove the successor's completion.

Understanding and Resolving Scheduling Conflict - Dependency order is violated

Option 2 - Wrong actual start date on successor

Is the actual progress on successor (row #4) mistaken? The actual start date was on April 29th or later?

Understanding and Resolving Scheduling Conflict - Dependency order is violated

Adjust the Actual Start to April 29th or a later date.

Understanding and Resolving Scheduling Conflict - Dependency order is violated

Option 3 - Wrong actual end date on predecessor

Check the recorded actual values on predecessor (row #3). Compare with the real values of progress.

Is the entered end date incorrect? Was the predecessor already completed sometime before the start of the successor on row #4? Let's assume it was April 27th at 5:00 PM.

Understanding and Resolving Scheduling Conflict - Dependency order is violated

Adjust the Actual End on predecessor (row #3) to April 27th, at 5:00 PM or an earlier date.

Understanding and Resolving Scheduling Conflict - Dependency order is violated

Option 4 - Dependency not required

Through different team crews, different locations, changed work conditions, etc it was possible to work on #4 even while #3 wasn't completed.

Obviously, the End to Start dependency wasn't required.

Understanding and Resolving Scheduling Conflict - Dependency order is violated

Remove the End to Start dependency.

Understanding and Resolving Scheduling Conflict - Dependency order is violated

Option 5 - Fixed start date on successor

The successor (row #4) has no actual values.

Understanding and Resolving Scheduling Conflict - Dependency order is violated

Its start date is precise and fixed. (! indicates a fixed date)

Understanding and Resolving Scheduling Conflict - Dependency order is violated

If the start date on row #4 is binding, and as it is not yet behind, you may ignore the warning for now.

Option 6 - Fixed start date on successor but not necessary

However if this fixed date is not really binding just remove the start restriction.

Understanding and Resolving Scheduling Conflict - Dependency order is violated
Understanding and Resolving Scheduling Conflict - Dependency order is violated

Publié par Vicky Stamatopoulou le 28.04.2020 dans Produits
Mots-clés: merlin-project assistance

La magie du Merlin Project sur le Mac et l'iPad

Diagramme de Gantt, Kanban et carte heuristique sur Mac et iPad.
Essayez maintenant gratuitement pendant 30 jours.

Mac App Store