Understanding and Resolving Scheduling Conflict: Activity Starts after Entered Date

Merlin Project Support

From time to time we receive in support following question:
Why does Merlin show some text and dates in red?

Understanding and resolving scheduling conflict - Activity Starts after Entered Date

These are rows with scheduling conflicts.

Just hover with the mouse over a red colored text. Merlin will show the current scheduling conflict in a tool tip.

Understanding and resolving scheduling conflict - Activity Starts after Entered Date
Understanding and resolving scheduling conflict - Activity Starts after Entered Date

To see all scheduling conflicts, just call 'Window > Show warnings' and switch to the 'Scheduling' tab.

Understanding and resolving scheduling conflict - Activity Starts after Entered Date

The conflict Activity starts after entered date in the selected row comes from the fact that an exact start date and time point of 7:00 AM had been entered. This time point lies outside the working time, so Merlin pushes the group (and its children activities) to the next possible time point (that is at 8:00 AM).

This is the warning you see here.

Resolving this conflict

Option 1

Do you really want to schedule it at 7:00 AM?

Understanding and resolving scheduling conflict - Activity Starts after Entered Date

You need to fix the start date.

Understanding and resolving scheduling conflict - Activity Starts after Entered Date

Option 2

7:00 AM is not correct?
You can remove it or adjust to 8:00 AM.

Publié par Vicky Stamatopoulou le 14.03.2017 dans Produits
Mots-clés: merlin-project assistance

La magie du Merlin Project sur le Mac et l'iPad

Diagramme de Gantt, Kanban et carte heuristique sur Mac et iPad.
Essayez maintenant gratuitement pendant 30 jours.

Mac App Store