Are you already planning your projects with Merlin Project and know the advantages of dependencies for dynamic planning? Then find out in this article how the clever usage of dependencies may also support you with individual specifications.
How can Merlin Project, for example, map cost plans that contain a dynamic factor which is dependent on unplanned delays?
Merlin Project offers you more flexibility than the basic functions would suggest. Below you will find a possible step-by-step guide for your own implementation.
Construction site of a craft business is planned with a work performance of 40 hours, corresponding to 5 days of work for one resource at 8 hours of work per day. At the same time, the business incurs additional fixed costs of 500 Euros per week.
Use an existing project or create a new, empty project first.
Creating Resources
Now switch view to Resources > Entry and
Entering resource cost rates
Creating Tasks
Switch to the view Work Breakdown > Entry and establish the following items:
Specifying the Work and Assigning Resources
Creating Dependencies
For creating the following dependencies, we recommend using the mouse or trackpad.
Cost Overview While Meeting Specifications
Switch to view Work Breakdown > Cost Expectation. According to the cost specifications of your project 2000,00 € in labor costs for 5 days of work plus 500,00 € in additional costs for the first week are expected.
Impact of a Delay
Now switch back to view Work Breakdown > Entry.
Merlin Project on the Mac or iPad offers you more flexibility than the basic functions suggest. Many everyday challenges can be realized with a clever combination of the functions offered.