Version 3.1.6
Changes
- Newly created activities are now shifted to the current date, even in in views using coarser time units.
Fixed issues
- Improved general stability.
- In some time zones, exception dates in exported calendars could be a day off.
- Improved the import of MS Project and XML files.
- Image exports of the detail view did always contain the whole project.
- Under some circumstances, the critical path was not displayed correctly.
- Sometimes, activating the time-phase description in the view options did not work.
- Saving a document with media to a different volume did fail with an error message.
- Fixed issues when working in folders shared by Egnyte.
- PDF exports of large projects could not be opened in Acrobat Reader.