Version 3.1.4
Changes
- Per-project base costs of resources are now included in the following fields: Planned Costs, Planned Work Costs, Expected Costs, Expected Work Costs, Actual Costs, Actual Work Costs
Fixed bugs
- Improved general stability.
- Fixed some issues which occurred when importing or exporting MS Project documents.
- When switching to the report view, the application could crash.
- In some cases, LDAP searches in the Library did not work properly.
- "Search & Replace" did not work in all cases.
- The names in the project column and the name of the root activity could differ.
- Copying rows from the attachments view to a text document did not work.
- Clicking the "Today" button in a popup calendar did sometimes show the wrong day.
- Closing a popup calendar could sometimes close the document window.
- Some exported XML documents could not be opened again.