Software selection and implementation
|
|
|
|
|
|
1
|
|
Management documents
|
|
|
|
|
|
2
|
|
Creation of target scenario/vision
|
|
|
|
|
|
3
|
|
Creation of preliminary specification
|
|
|
|
2
|
|
4
|
|
ABC analysis
|
|
|
|
3
|
|
5
|
|
Feasibility study
|
|
|
|
4
|
|
6
|
|
Risk analysis
|
|
|
|
5
|
|
7
|
|
Create underlying documents
|
|
|
|
1
|
|
8
|
|
Form internal project team
|
|
|
|
7
|
|
9
|
|
Management requirements on forming the team
|
|
|
|
|
|
10
|
|
Candidate interviews
|
|
|
|
9
|
|
11
|
|
Initial team meeting
|
|
|
|
10
|
|
12
|
|
Internal team agreed
|
|
|
|
8
|
|
13
|
|
Vendor pre-selection
|
|
|
|
7
|
|
14
|
|
Vendor research
|
|
|
|
|
|
15
|
|
Vendor documentation
|
|
|
|
14
|
|
16
|
|
Develop questionnaire
|
|
|
|
15
|
|
17
|
|
Send questionnaire to pre-selected vendors
|
|
|
|
16
|
|
18
|
|
Processing time
|
|
|
|
17
|
|
19
|
|
Vendor selection
|
|
|
|
18
|
|
20
|
|
Vendor pre-selection complete
|
|
|
|
13
|
|
21
|
|
Vendor review
|
|
|
|
20
|
|
22
|
|
Invitation to presentation
|
|
|
|
|
|
23
|
|
Presentation 1
|
|
|
|
22
|
|
24
|
|
Presentation 2
|
|
|
|
23
|
|
25
|
|
Presentation 3
|
|
|
|
24
|
|
26
|
|
Presentation 4
|
|
|
|
25
|
|
27
|
|
Presentation 5
|
|
|
|
26
|
|
28
|
|
Evaluation of presentations
|
|
|
|
27
|
|
29
|
|
Proposal 1
|
|
|
|
28
|
|
30
|
|
Proposal 2
|
|
|
|
29SS
|
|
31
|
|
Proposal 3
|
|
|
|
29SS
|
|
32
|
|
Negotiations 1
|
|
|
|
29
|
|
33
|
|
Negotiations 2
|
|
|
|
32SS
|
|
34
|
|
Negotiations 3
|
|
|
|
33SS
|
|
35
|
|
Decision
|
|
|
|
32; 33; 34
|
|
36
|
|
Vendor pitch complete
|
|
|
|
21
|
|
37
|
|
Awarding of contract
|
|
|
|
36
|
|
38
|
|
Review proposal documentation
|
|
|
|
|
|
39
|
|
Financial review
|
|
|
|
|
|
40
|
|
Legal review
|
|
|
|
|
|
41
|
|
Technical review
|
|
|
|
|
|
42
|
|
Strategic review
|
|
|
|
|
|
43
|
|
Formulate proposal
|
|
|
|
38
|
|
44
|
|
Consolidate proposal documentation
|
|
|
|
43
|
|
45
|
|
Order signed
|
|
|
|
37
|
|
46
|
|
Project kick-off event
|
|
|
|
45
|
|
47
|
|
Supporting workshop
|
|
|
|
|
|
48
|
|
Creation of solution matrix
|
|
|
|
47
|
|
49
|
|
Task matrix
|
|
|
|
48
|
|
50
|
|
Get-together
|
|
|
|
49
|
|
51
|
|
Kick-off complete
|
|
|
|
46
|
|
52
|
|
Review processes
|
|
|
|
51
|
|
53
|
|
Process group 1
|
|
|
|
|
|
54
|
|
Documentation of current processes
|
|
|
|
|
|
55
|
|
Optimization of current processes
|
|
|
|
54SS
|
|
56
|
|
Review of new solution
|
|
|
|
54
|
|
57
|
|
Process group 2
|
|
|
|
53
|
|
58
|
|
Documentation of current processes
|
|
|
|
|
|
59
|
|
Optimization of current processes
|
|
|
|
58SS
|
|
60
|
|
Review of new solution
|
|
|
|
58
|
|
61
|
|
Process group 3
|
|
|
|
57
|
|
62
|
|
Documentation of current processes
|
|
|
|
|
|
63
|
|
Optimization of current processes
|
|
|
|
62SS
|
|
64
|
|
Review of new solution
|
|
|
|
62
|
|
65
|
|
Process group 4
|
|
|
|
61
|
|
66
|
|
Documentation of current processes
|
|
|
|
|
|
67
|
|
Optimization of current processes
|
|
|
|
66SS
|
|
68
|
|
Review of new solution
|
|
|
|
66
|
|
69
|
|
Process group 5
|
|
|
|
65
|
|
70
|
|
Documentation of current processes
|
|
|
|
|
|
71
|
|
Optimization of current processes
|
|
|
|
70SS
|
|
72
|
|
Review of new solution
|
|
|
|
70
|
|
73
|
|
Process group 6
|
|
|
|
69
|
|
74
|
|
Documentation of current processes
|
|
|
|
|
|
75
|
|
Optimization of current processes
|
|
|
|
74SS
|
|
76
|
|
Review of new solution
|
|
|
|
74
|
|
77
|
|
Process group 7
|
|
|
|
73
|
|
78
|
|
Documentation of current processes
|
|
|
|
|
|
79
|
|
Optimization of current processes
|
|
|
|
78SS
|
|
80
|
|
Review of new solution
|
|
|
|
78
|
|
81
|
|
Process group 8
|
|
|
|
77
|
|
82
|
|
Documentation of current processes
|
|
|
|
|
|
83
|
|
Optimization of current processes
|
|
|
|
82SS
|
|
84
|
|
Review of new solution
|
|
|
|
82
|
|
85
|
|
Process group 9
|
|
|
|
81
|
|
86
|
|
Documentation of current processes
|
|
|
|
|
|
87
|
|
Optimization of current processes
|
|
|
|
86SS
|
|
88
|
|
Review of new solution
|
|
|
|
86
|
|
89
|
|
Process group 10
|
|
|
|
85
|
|
90
|
|
Documentation of current processes
|
|
|
|
|
|
91
|
|
Optimization of current processes
|
|
|
|
90SS
|
|
92
|
|
Review of new solution
|
|
|
|
90
|
|
93
|
|
Process analysis complete
|
|
|
|
52
|
|
94
|
|
Data analysis
|
|
|
|
51
|
|
95
|
|
Review of old data state
|
|
|
|
|
|
96
|
|
Comparison of old and new data structure
|
|
|
|
95
|
|
97
|
|
Data migration strategy
|
|
|
|
96
|
|
98
|
|
Data analysis complete
|
|
|
|
94
|
|
99
|
|
Implement function blocks
|
|
|
|
98
|
|
100
|
|
Function block 1
|
|
|
|
53
|
|
101
|
|
Specify approach for FB
|
|
|
|
|
|
102
|
|
Specify workflows for FB
|
|
|
|
101
|
|
103
|
|
Review risks for FB
|
|
|
|
102
|
|
104
|
|
Customization
|
|
|
|
103
|
|
105
|
|
Confirm requirements
|
|
|
|
|
|
106
|
|
Holding the event
|
|
|
|
105
|
|
107
|
|
Checking
|
|
|
|
106
|
|
108
|
|
Tests
|
|
|
|
107
|
|
109
|
|
Implementation
|
|
|
|
104
|
|
110
|
|
Employee training
|
|
|
|
109
|
|
111
|
|
Test using basic installation
|
|
|
|
109
|
|
112
|
|
FB 1 complete
|
|
|
|
100
|
|
114
|
|
Specify approach for FB
|
|
|
|
|
|
115
|
|
Specify workflows for FB
|
|
|
|
114
|
|
116
|
|
Review risks for FB
|
|
|
|
115
|
|
117
|
|
Customization
|
|
|
|
116
|
|
118
|
|
Confirm requirements
|
|
|
|
|
|
119
|
|
Holding the event
|
|
|
|
118
|
|
120
|
|
Checking
|
|
|
|
119
|
|
121
|
|
Tests
|
|
|
|
120
|
|
122
|
|
Implementation
|
|
|
|
117
|
|
123
|
|
Test using existing FBs
|
|
|
|
122
|
|
124
|
|
Employee training
|
|
|
|
123
|
|
125
|
|
FB 2 complete
|
|
|
|
113
|
|
126
|
|
Function block 3
|
|
|
|
61; 125
|
|
127
|
|
Specify approach for FB
|
|
|
|
|
|
128
|
|
Specify workflows for FB
|
|
|
|
127
|
|
129
|
|
Review risks for FB
|
|
|
|
128
|
|
130
|
|
Customization
|
|
|
|
129
|
|
131
|
|
Confirm requirements
|
|
|
|
|
|
132
|
|
Holding the event
|
|
|
|
131
|
|
133
|
|
Checking
|
|
|
|
132
|
|
134
|
|
Tests
|
|
|
|
133
|
|
135
|
|
Implementation
|
|
|
|
130
|
|
136
|
|
Test using existing FBs
|
|
|
|
135
|
|
137
|
|
Employee training
|
|
|
|
136
|
|
138
|
|
FB 3 complete
|
|
|
|
126
|
|
139
|
|
Function block 4
|
|
|
|
65; 138
|
|
140
|
|
Specify approach for FB
|
|
|
|
|
|
141
|
|
Specify workflows for FB
|
|
|
|
140
|
|
142
|
|
Review risks for FB
|
|
|
|
141
|
|
143
|
|
Customization
|
|
|
|
142
|
|
144
|
|
Confirm requirements
|
|
|
|
|
|
145
|
|
Holding the event
|
|
|
|
144
|
|
146
|
|
Checking
|
|
|
|
145
|
|
147
|
|
Tests
|
|
|
|
146
|
|
148
|
|
Implementation
|
|
|
|
143
|
|
149
|
|
Test using existing FBs
|
|
|
|
148
|
|
150
|
|
Employee training
|
|
|
|
149
|
|
151
|
|
FB 4 complete
|
|
|
|
139
|
|
152
|
|
Function block 5
|
|
|
|
69; 151
|
|
153
|
|
Specify approach for FB
|
|
|
|
|
|
154
|
|
Specify workflows for FB
|
|
|
|
153
|
|
155
|
|
Review risks for FB
|
|
|
|
154
|
|
156
|
|
Customization
|
|
|
|
155
|
|
157
|
|
Confirm requirements
|
|
|
|
|
|
158
|
|
Holding the event
|
|
|
|
157
|
|
159
|
|
Checking
|
|
|
|
158
|
|
160
|
|
Tests
|
|
|
|
159
|
|
161
|
|
Implementation
|
|
|
|
156
|
|
162
|
|
Test using existing FBs
|
|
|
|
161
|
|
163
|
|
Employee training
|
|
|
|
162
|
|
164
|
|
FB 5 complete
|
|
|
|
152
|
|
165
|
|
Function block 6
|
|
|
|
73; 138; 164
|
|
166
|
|
Specify approach for FB
|
|
|
|
|
|
167
|
|
Specify workflows for FB
|
|
|
|
166
|
|
168
|
|
Review risks for FB
|
|
|
|
167
|
|
169
|
|
Customization
|
|
|
|
168
|
|
170
|
|
Confirm requirements
|
|
|
|
|
|
171
|
|
Holding the event
|
|
|
|
170
|
|
172
|
|
Checking
|
|
|
|
171
|
|
173
|
|
Tests
|
|
|
|
172
|
|
174
|
|
Implementation
|
|
|
|
169
|
|
175
|
|
Test using existing FBs
|
|
|
|
174
|
|
176
|
|
FB 6 complete
|
|
|
|
165
|
|
177
|
|
Function block 7
|
|
|
|
77; 176
|
|
178
|
|
Specify approach for FB
|
|
|
|
|
|
179
|
|
Specify workflows for FB
|
|
|
|
178
|
|
180
|
|
Review risks for FB
|
|
|
|
179
|
|
181
|
|
Customization
|
|
|
|
180
|
|
182
|
|
Confirm requirements
|
|
|
|
|
|
183
|
|
Holding the event
|
|
|
|
182
|
|
184
|
|
Checking
|
|
|
|
183
|
|
185
|
|
Tests
|
|
|
|
184
|
|
186
|
|
Implementation
|
|
|
|
181
|
|
187
|
|
Test using existing FBs
|
|
|
|
186
|
|
188
|
|
Employee training
|
|
|
|
187
|
|
189
|
|
FB 7 complete
|
|
|
|
177
|
|
190
|
|
Function block 8
|
|
|
|
81; 189
|
|
191
|
|
Specify approach for FB
|
|
|
|
|
|
192
|
|
Specify workflows for FB
|
|
|
|
191
|
|
193
|
|
Review risks for FB
|
|
|
|
192
|
|
194
|
|
Customization
|
|
|
|
193
|
|
195
|
|
Confirm requirements
|
|
|
|
|
|
196
|
|
Holding the event
|
|
|
|
195
|
|
197
|
|
Checking
|
|
|
|
196
|
|
198
|
|
Tests
|
|
|
|
197
|
|
199
|
|
Implementation
|
|
|
|
194
|
|
200
|
|
Test using existing FBs
|
|
|
|
199
|
|
201
|
|
Employee training
|
|
|
|
200
|
|
202
|
|
FB 8 complete
|
|
|
|
190
|
|
203
|
|
Function block 9
|
|
|
|
85; 202
|
|
204
|
|
Specify approach for FB
|
|
|
|
|
|
205
|
|
Specify workflows for FB
|
|
|
|
204
|
|
206
|
|
Review risks for FB
|
|
|
|
205
|
|
207
|
|
Customization
|
|
|
|
206
|
|
208
|
|
Confirm requirements
|
|
|
|
|
|
209
|
|
Holding the event
|
|
|
|
208
|
|
210
|
|
Checking
|
|
|
|
209
|
|
211
|
|
Tests
|
|
|
|
210
|
|
212
|
|
Implementation
|
|
|
|
207
|
|
213
|
|
Test using existing FBs
|
|
|
|
212
|
|
214
|
|
Employee training
|
|
|
|
213
|
|
215
|
|
FB 9 complete
|
|
|
|
203
|
|
216
|
|
Function block 10
|
|
|
|
89; 215
|
|
217
|
|
Specify approach for FB
|
|
|
|
|
|
218
|
|
Specify workflows for FB
|
|
|
|
217
|
|
219
|
|
Review risks for FB
|
|
|
|
218
|
|
220
|
|
Customization
|
|
|
|
219
|
|
221
|
|
Confirm requirements
|
|
|
|
|
|
222
|
|
Holding the event
|
|
|
|
221
|
|
223
|
|
Checking
|
|
|
|
222
|
|
224
|
|
Tests
|
|
|
|
223
|
|
225
|
|
Implementation
|
|
|
|
220
|
|
226
|
|
Test using existing FBs
|
|
|
|
225
|
|
227
|
|
Employee training
|
|
|
|
226
|
|
228
|
|
FB 10 complete
|
|
|
|
216
|
|
229
|
|
Function blocks implemented
|
|
|
|
99
|
|
230
|
|
Data migration test
|
|
|
|
229
|
|
231
|
|
Delete test data
|
|
|
|
|
|
232
|
|
Current data export and import
|
|
|
|
231
|
|
233
|
|
Plausibility check
|
|
|
|
232
|
|
234
|
|
Data migration test complete
|
|
|
|
230
|
|
235
|
|
Overall acceptance test
|
|
|
|
234
|
|
236
|
|
Test run 1
|
|
|
|
|
|
237
|
|
Test run 2
|
|
|
|
236
|
|
238
|
|
Test run 3
|
|
|
|
|
|
239
|
|
Test run 4
|
|
|
|
237
|
|
240
|
|
Corrections
|
|
|
|
239
|
|
241
|
|
Overall acceptance test complete
|
|
|
|
235
|
|
242
|
|
Live installation
|
|
|
|
241
|
|
243
|
|
Hardware integration
|
|
|
|
|
|
244
|
|
Network integration
|
|
|
|
243
|
|
245
|
|
Installation
|
|
|
|
244
|
|
246
|
|
Data transfer
|
|
|
|
245
|
|
247
|
|
Live installation complete
|
|
|
|
242
|
|
248
|
|
Parallel live operation with old system
|
|
|
|
247
|
|
249
|
|
Start of live operation
|
|
|
|
248
|
|
250
|
|
Launch party
|
|
|
|
249
|
|
251
|
|
Project complete
|
|
|
|
250
|
|
252
|
|
Lessons learned workshop
|
|
|
|
|
|
253
|
|
Team disbanded
|
|
|
|
252
|
|
254
|
|
Final milestones Project end
|
|
|
|