Architect; Client; Bank; Excavator; Builder; Electrician; Scaffolding company; Carpenter; Roofer; Plumber; Installer; Tiler; Joiner; Painter
|
|
|
|
|
Pre-planning
|
|
Architect; Client
|
|
|
Hand-drawn sketch
|
|
Architect; Client
|
|
|
|
|
|
|
|
|
First proposal worked out
|
|
Architect
|
|
|
First proposal worked out
|
|
|
|
|
|
|
|
|
Outline planning
|
|
Architect; Client
|
|
|
Draw 100:1 scale plans
|
|
Architect
|
|
|
|
|
|
|
Planning application
|
|
Client
|
|
|
|
|
|
|
Produce structural analysis
|
|
|
|
|
|
|
In-depth planning
|
|
Architect
|
|
|
Draw 50:1 scale plans
|
|
Architect
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Bank meeting
|
|
Client; Bank
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Shell construction
|
|
Excavator; Builder; Electrician; Scaffolding company; Carpenter; Roofer; Plumber
|
|
|
|
|
Basement
|
|
Excavator; Builder; Electrician
|
|
|
Digging of foundations
|
|
Excavator
|
|
|
|
|
|
|
|
|
|
|
|
|
Pour concrete floor
|
|
Builder
|
|
|
|
|
|
|
Erect external wall formwork
|
|
Builder
|
|
|
Erect external wall formwork
|
|
|
|
|
|
|
Pour concrete to form basement walls
|
|
Builder
|
|
|
Pour concrete to form basement walls
|
|
|
|
|
|
|
|
|
|
|
|
|
Construct internal walls
|
|
Builder
|
|
|
|
|
|
|
Supports for basement ceiling
|
|
Builder
|
|
|
Supports for basement ceiling
|
|
|
|
|
|
|
Lay concrete slabs
|
|
Builder
|
|
|
|
|
|
|
Electrical work (lay ceiling wiring)
|
|
Electrician
|
|
|
Electrical work (lay ceiling wiring)
|
|
|
|
|
|
|
Pour concrete to form basement stairs and ceiling
|
|
Builder
|
|
|
Pour concrete to form basement stairs and ceiling
|
|
|
|
|
|
|
|
|
Ground floor
|
|
Builder; Excavator; Electrician
|
|
|
Construct external walls
|
|
Builder
|
|
|
|
|
|
|
Construct internal walls
|
|
Builder
|
|
|
|
|
|
|
|
|
|
|
|
|
Supports for ground floor ceiling
|
|
Builder
|
|
|
Supports for ground floor ceiling
|
|
|
|
|
|
|
Lay concrete slabs
|
|
Builder
|
|
|
|
|
|
|
Electrical work (lay ceiling wiring)
|
|
Electrician
|
|
|
Electrical work (lay ceiling wiring)
|
|
|
|
|
|
|
Pour concrete to form ground floor stairs and ceiling
|
|
Builder
|
|
|
Pour concrete to form ground floor stairs and ceiling
|
|
|
|
|
|
|
|
|
First floor
|
|
Scaffolding company; Builder; Carpenter; Roofer; Plumber
|
|
|
Erect scaffolding
|
|
Scaffolding company
|
|
|
|
|
|
|
Construct gable and knee walls
|
|
Builder
|
|
|
Construct gable and knee walls
|
|
|
|
|
|
|
Construct internal walls
|
|
Builder
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Interior work
|
|
Electrician; Installer; Plumber; Builder; Tiler; Joiner; Carpenter; Painter
|
|
|
Electrical work
|
|
Electrician
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Joinery work (exterior)
|
|
Joiner
|
|
|
|
|
|
|
Drywall construction work
|
|
Carpenter
|
|
|
Drywall construction work
|
|
|
|
|
|
|
|
|
|
|
|
|
Roller shutter work
|
|
Electrician
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Joinery work (interior)
|
|
Joiner
|
|
|
|
|
|
|
Handover of keys
|
|
Architect; Client
|
|
|
|
|
|
|
|
|