Can I define the Critical Path?

Merlin Project automatically recognizes whether or not activities are on critical path. On forwards planned projects, they are the activities which may change the end of the project.

If you have for example just two activities (A and B) starting today with a duration of 2 for A and 5 days for B. ,Activity B' with the longer duration (5 days) defines the end of the project and it is thus on critical path.

Read more...