Vicky Stamatopoulou on 21. March 2013
Those of you who have checked our new post series about “Merlin report templates” know by now…
Now let’s do some magic with the reports.
Work Chart
If you like to report expected or actual working hours per resource in a chart and/or table, this is a custom report doing so.
You may check contained ‘WorkChart.py’, “WorkChart.wbl” to see how we iterate in project’s master resources, ask for their working units, compare them with total work hours and output this information in the table. In the pie chart, working hours are forwarded and the pie chart calculates respective percentages. There are methods in the Python part gathering the x- and y-Ticks and some javascript functions drawing the graph. You may furthermore disable outputting resources’ work in the table and define the first 8 colours to be used for the pie chart.
Feel free to modify this custom report further as you require for your needs.
An output sample:
Showing expected work hours by resource.
And the report options: (more…)
Tags: Chart, Customize, Merlin report template, Reports, Resources, Template, Work
Vicky Stamatopoulou on 15. March 2013
Those of you who have checked our new post series about “Merlin report templates” know by now…
Now let’s do some magic with the reports.
Working hours distributed in time per resource and assignment
If you like to report the distribution in time of expected or actual working hours per resource and assignment, this is a custom report template to use.
You may check contained ‘AssignmentDistribution.py’, “AssignmentDistribution.wbl” to see how we iterate in project’s master resources, ask for their assignments and iterate in time to show the amount of expected or actual work in the selected time interval units.
Feel free to modify this custom report further as you require for your needs.
An output sample:
Showing work hours by resource and week.
Or resources’ assignments by month (more…)
Tags: Assignment, Customize, Merlin report template, Reports, Resources, Template, Work distribution, Work hours
Vicky Stamatopoulou on 22. February 2012
Those of you who have checked our new post series about “Merlin report templates” know by now…
Now let’s do some magic with the reports.
What if you want to report expected or actual resources’ work per phase?
We have used the report template as posted in this thread of Merlin’s user forum in Google.
Changed the methods asking for resource costs to ask for resource expected or actual work.

Tags: Customize, Merlin report template, Reports, Resources, Templates, Work
Vicky Stamatopoulou on 19. September 2011
In Merlin you can define the role of a resource and specify it thus a bit better. Merlin comes with a predefined list of resource roles. You will find them listed in the ‘info’ inspector by a selected resource and in the project settings (File > Project Settings > Value Lists > Resource). To define the role of your resource, select it first, switch to the “Info” inspector and select the desired role.
What happens if you don’t find the specific role in the list?
You may ‘Add’ a new resource role in the project settings while viewing the resources’ roles

OR…
just enter it in the (more…)
Vicky Stamatopoulou on 18. November 2010
One of the reasons why I love Merlin is because it is not stressing you into work the way it wants. It allows you to go your way. Take assigning tasks onto resources for example.
You have various possibilities to do so:

Tags: Assigned Resources, Assignments, Merlin, Merlin 101, Resources
Vicky Stamatopoulou on 11. May 2010
![]()
Does Merlin have master resources or a resources pool?
In Merlin you can add resources,
To open the library call Window > Show Library or use the according button of the toolbar:
Tags: Master Resources, Merlin, Resources, Resources pool
Vicky Stamatopoulou on 20. April 2010
Sometimes you plan activities in projects, which can be done by equipment. Machines or computer which may run unattended, do not need regular working hours and can work 24h a day, 7days a week. Surely you have assigned real person as resources for activities in the past and you know how to do this in Merlin, but how to proceed when having equipment resources?
The good news? This is as easy as setting up person resources.
Tags: 24h, Calendar, Equipment, Merlin, Merlin 101, Resources
Vicky Stamatopoulou on 20. April 2010
Merlin supports many types of resources. They are:
Materials differ from the other types in that they don’t do any of the work on which they are assigned to and have an option for you to determine their measuring unit. For example, you can choose the material unit “kg” , and your standard rate becomes cost per kg.
If you like to use another unit (‘piece’ for example ) than the pre-defined ones, simply type it in the appropriate text edit field of the inspector:
Tags: Custom units, Material, Materials, Merlin, Merlin 101, Resources, Units
John Kranz on 16. July 2009
One of the benefits of using Merlin is tracking resource utilization*.
Just take a look in the Gantt chart of the Utilization view. Color coded bars and percentage information visualize overall resource utilization in the current scale of the timeline.
Related to this feature, we often hear from customers who wish to customize the threshold levels controlling the yellow-green-red colors.
Tags: Master Resources, Merlin, Merlin 101, Over-Utilization, Resources, Utilization, Utilization level threshold