Vicky Stamatopoulou on 15. June 2010
From time to time we receive requests on how to set up a global unit for calculated durations. So for example:
…when planning my project in Merlin, the calculated duration of the project is
shown in a dynamic unit, i.e. day, week, month, year, depending on the
length of the activity. How do I fix it to show weeks? We mainly operate in
weeks…
Well nothing simpler than that. Just call File > Project settings and select in the ‘General’ tab the desired unit for ‘Calculated Durations’…
Easy? Hey we’ve told you so
Watch the video on YouTube
Tags: Durations, Merlin, Merlin 101, Units
No comments yet.
RSS feed for comments on this post. TrackBack URL